Updated manuals and a totally new Appendix

September 18, 2025 8:32 CEST
Some updated manuals for SSAB Pile products and a totally new Appendix.

Preheating and cooling of splice welds

Appendix 5 for the Design and installation manual of RR® and RD® piles has been updated. The Appendix considers preheating and cooling of splice welds. There have been some updates to the EN standards, some updated values for weld consumables and the tables for required preheat have been re-calculated with the latest material properties.

The Appendix 5 gives instructions on preheat of the piles before welding. Required preheat depends on the material properties of the steel and weld consumable. It is used to avoid possible hydrogen cracking in the welds. Preheat delays the cooling of the weld region and therefore promotes hydrogen effusion. Preheat also reduces the state of internal stresses. The preheat temperatures given in the Appendix 5 have been calculated according to methods given in EN 1011-2 standard.

Beside instructions for preheat, the Appendix 5 gives also instructions for cooling of the welds before performing a Non-Destructive Testing (NDT). It presents the correct hold times for SSAB Pile products based on the instructions given in EN 1090-2. For steel grade S550J2H the instructions in EN 1090-2 have been updated and now these new instructions have been implemented to the Appendix 5.

Naturally the Appendix 5 can be applied for RR and RD piles, but also for RD pile walls.

Resistance tables for RR® and RD® piles in Sweden

The Appendixes A and B for the Swedish version of the Design and installation manual for RR and RD piles contain vast amount of pre-calculated table values for the resistances of RR and RD piles. The tables include resistance values for geotechnical resistances and for structural buckling resistances.

The new values have been calculated with the latest version of PileCalc, the free-to-use design tool for SSAB Pile products. The calculations for composite effect piles follow the instructions given in the Pålkommissionen report 108.

Totally new Appendix 1 for the Design and installation manual for RD® pile walls

This totally new Appendix 1 gives several examples for structural details and possible methods for implementation of RD pile wall structures. It supplements the manual by offering more information and ideas on several details related to RD pile walls.

The content of the Appendix 1 answers to many questions raised up during the past 15 years and over 350 projects accomplished with RD pile walls. It gives more detailed instructions for example on execution of splice welding of tubular piles equipped with connectors. It also shows some examples on details which can be used for external and internal support structures used with RD pile walls.

Where to download

All the downloadable material related to SSAB pile products can be downloaded from the below pages:

In English

In Finnish

In Swedish

More information on RR® and RD® piles and RD® pile wall www.ssab.com/infra

Attachments

Related articles

Sep 17Other press releases
Sustainability
Luleå
Fossil-free steel

Today construction of SSAB's new steel mill in Luleå started with the Minister for Energy, Business and Industry and Deputy Prime Minister Ebba Busch and SSAB's CEO Johnny Sjöström participating in a...

Sep 16Regulatory press releases
Investors

As previously disclosed, the Swedish Financial Supervisory Authority (FI) opened a review in March 2025 regarding the disclosure around the goodwill impairment reported by SSAB in December 2022. FI...

Sep 4Regulatory press releases
Capital markets day

SSAB´s Capital Markets Day will be held at SSAB´s steel mill in Oxelösund, Sweden on November 4, 2025. The day will provide insights into SSAB´s offering of high-strength steels and other premium...